As one of the fastest growing school districts in British Columbia, we are constantly planning for the future. Future growth is projected to bring in upwards of 300-500 new students each year, our district plans today so that we can provide students, staff and communities with great infrastructure tomorrow.
Please take a moment to look over our plans to see how we will accommodate and shift for rapid growth.
Capital Plan Submission & Long Range Facilities Plan
This is a current update on projects like new schools, expansions, upgrades and replacements.
- 2022-23 Capital Plan Submission
- Long Range Facilities Plan
- Minor capital projects approved for 2023-24
Capital Projects
As a growing school district, we are always planning ahead for future growth. Our Board of Education continuously advocates to the provincial government to secure funding for new schools, expansions and upgrade projects.
The chart below outlines our major capital projects including new school construction, seismic replacements projects, and expansions.
Project | Project Description | Current Status | Date of Approval | Occupancy |
---|---|---|---|---|
Royal Bay Secondary Expansion | Addition of 600 student spaces | Complete | Feb 2018 | Sept 2020 |
PEXSISEN Elementary | New school (capacity 500) | Complete | Mar 2019 | Sept 2022 |
Centre Mountain Lellum Middle | New School (capacity 700) | Complete | Mar 2019 | Nov 2022 |
SĆIȺNEW̱ SṮEȽIṮḴEȽ Elementary in South Langford | New School (capacity 480) | Approved | June 2022 | Sept 2025 (expected) |
Elementary in South Colwood | New School (capacity 480) | Seeking Approval | ||
Elementary in North Langford |
New School (capacity 480) |
Seeking Approval | ||
Port Renfrew Elementary | Seismic Replacement | Approved | March 2024 | Fall 2025 (expected) |
Secondary in North Langford | New School (capacity 800-1000) | Seeking Approval | ||
Elementary in Sun River | New School (capacity 480) | Seeking Approval | ||
Middle School in North Langford | New School | Seeking Approval |